PORTO HOUSE ESTIMATES:

Overview

To completely renovate the apartment.

  1. Duration of project: 20-24 weeks.
  2. To maintain the budget outlined below.
  3. To ensure high-standard workmanship and timely delivery.
  4. To achieve the client’s desired aesthetic.

Specifications :

DEMOLITION:

  • GROUND FLOOR

Remove garbage Remove the wall ‘s plaster Digging the floor Open a new window TOTAL 3500

  • MID FLOOR

Removal of the wall between kitchen and living room Removal of the floor Removal of the wall between bathrooms wall and stair cases Removal bathroom ‘s and kitchen’s tiles Removal of the Plaster boards between bedroom and livingroom Removal of all the bedrooms walls Removal of all the bathroom’s walls Removal of the windows Rubbish and garbage TOTAL 2200

  • UPPER FLOOR

Removal of the arches Removal of the bathroom’s walls Removal of the bedrooms walls Removal of the loft space between ceiling and roof Removal all the ceiling Removal of the bathroom’s tiles Removal of the bathrooms kabinets Removal of the wardrobe Removal of the windows Removal of the kitchen cabinets Removal of the window’s sills Removal of the radiators Removal of the kitchen tiles Throwing rubbish and garbage Removal the concrete belt TOTAL 2800

GRAND TOTAL 8,500

ROOF WORKS

Installation of new roof:

  • Roof ceramic
  • Roof insulation
  • Roof belt
  • Roof Wooden construction
  • Installation of Raining drainages system

GRAND TOTAL 14,400

WALL WORKS AND PLASTERING:

  • GROUND FLOOR:

Application of the concrete on the floor Mounting of the Bathroom’s walls Building back wall on the rock Mounting of the Bedroom’s walls Ceiling plastering Walls plastering Window plastering TOTAL 16.500

  • MID FLOOR:

Mounting the wall between the living room and the bedroom Mounthing the wall between the bathroom and the bedroom Application of the screed on the kitchen”s walls Applications of the screed plaster on the livingroom and bathroom walls Application of the concrete floor and iron beams in stead of stairscases exit Application of the screed plaster on the bathrooms walls Application of the bew concrete floor GROUND TOTAL 12300

  • UPPER FLOOR

Application of the screed plastering on the bedroom’s walls Mounting of the loft’s walls Mounthing of the walls of the staircase loft ‘s exit Building the iron stair cases constructions Screed plastering of the bathroom ‘s and kicthen ‘s walls Screed plastering at the bedroom’s walls Installation of the ceiling “s iron beam and supporting wall’s iron beam to reinforce the loft construction Application of the plaster boards to cover the Iron beam Screed Plastering of the beam’s plaster boards GROUND TOTAL 11500

  • LOFT FLOOR

Application of new wooden floor Mounting of the plaster board walls Installation of Terrace’s concrete floor Mounting of terrace ‘s walls and wall’s plastering GROUND TOTAL 9500

GRAND TOTAL 49800

PAINTING

  • LOWER FLOOR 3.400,00
  • MIDDLE FLOOR 3.400,00
  • GROUND FLOOR 3.400.00
  • LOFT FLOOR 2.600.00

Note : Materials and workmanship included. GRAND TOTAL 12800

UPPER FLOOR STAIRS WORK

  • New stairs steps from wood with aluminum handle
  • Staircase glass wall “s separation

TOTAL 4500

TILES APPLICATION ;

LABOR PRICES ( 35 EUR per m2)

  • UPPER FLOOR 91 m2

bathroom Kitchen wall Marble tiles at the bedroom and entrance floor since we have marble door in the living room Balcony TOTAL : 3185

  • MIDDLE FLOR 81m2

Kitchen wall Kitchen Floors Bedroom Balcony TOTAL 2835

  • GROUND FLOOR 90 m2

Bathroom Kitchen wall Kitchen floor Bedroom Living Room TOTAL 3150

  • terrace tiles 20 m2

TOTAL 700

  • Tiles and supporting materials prices 282 m2 x 25 EUR per : 7050

GRAND TOTAL tiles labour 9870+ materials 7050 =16920

Application of parquet :

Parquet prices (33,20 EauR per m2)

  • Loft floor 42 m2
  • Mid floor 24 m2

Total :2058

  • Labour : (15 EUR per m2 ) 930

GRAND TOTAL : 2988

ELECTRIC INFRASTRUCTURE SYSTEM :

  • UPPER FLOOR

Electric installation new kitchen bedroom living room bathroom balcony and AC TOTAL 2.400

  • MIDDLE FLOOR

Electric installation new kitchen bedroom living room bathroom balcony and AC TOTAL 2,400

  • GROUND FLOOR

Electric installation new kitchen bedroom living room bathroom out side entrance and AC TOTAL 2,400

  • LOFT FLOOR

Electric installation new Staircase bedroom Terrace sun panel and AC TOTAL 1,600,00€

GRAND TOTAL 8,800

PLUMBING :

  • UPPER FLOOR

Installation of the new pipes and drainage system in the kitchen and the bathroom Installation of Sun's panels and water pipes Installation of shower / sink in the bathroom and the kitchen Installation of 2 air conditioners TOTAL 2.800

  • MIDDLE FLOOR

Installation of the new pipes and drainage system in the kitchen and the bathroom Installation of water pipes Installation of shower/ sink in the bathroom and the kitchen Installation of 2 air conditioners TOTAL 2400

  • GROUND FLOOR

Installation of the new pipes and drainage system in the kitchen and the bathroom Installation of water pipes Installation of shower / sink in the bathroom and sink kitchen centrally central municipal Installation 2 air conditioner TOTAL 2,600

GRAND TOTAL 7,800

WINDOWS:

  • LOWER FLOOR WINDOWS

2 balcony doors 3 windows 2 interior doors 1 entrance door TOTAL 6,700,00 Painting windows and doors 1,600

  • MIDDLE FLOOR WINDOWS

4 balcony doors 3 windows 2 interior doors 1 entrance door TOTAL 10,150,00 Painting windows and doors 2,000

  • GROUND FLOOR WINDOWS

3 windows 2 interiordoors 1 entrance door TOTAL 5,550,00€ Painting windows and doors 1,200

  • LOFT FLOOR WINDOWS

1 balcony door 1 window Total 2,100 Painting window and doors 400

GRAND TOTAL windows 24500+paint 5200=29700 was 30,850??

COUNTERTOP :

  • UPPER FLOOR

7 meter kitchen counter (including pediment) 120X80 centimeter island counter (200,00per m2 ) :1400 EUR Bathroom countertop : 120,00 SHOWER MARBLE WALLs SHELVES x3 : 100,00 Kitchen sink x 1 200,00 Total : 1820

  • MIDDLE FLOOR

7 meter kitchen counter (including pediment) (200 EUR per m2 ) 120x80 centimeter island counter: 1400 Bathroom countertop : 120,00 Bathroom marble wall shelves x 3: 100,00 Kitchen sink : 200,00 TOTAL : 1820

  • GROUND FLOOR

7 meter kitchen counter (including pediment) 120x80 cm island counter: 1500 Bathroom countertop : 120,00 Marble shower walls shelves x 3 : 100,00 Kitchen sink : 200,00 Total : 1820

GRAND TOTAL: 5460

BATHROOM AND KITCHEN ACCESSORIES

  • Toilet Stone
  • Drainage
  • Batroom sink faucet
  • Toilet stone shower spray
  • Long ( lineer ) towel hanger
  • Ring small towel hanger
  • Bathrope hanger
  • Soap dish
  • Toilet paper holder
  • Brush holder
  • Toilet brush
  • Trash can
  • Kitchen sink faucet

Note : Shipping and assembly fees are not included.

  • UPPER FLOOR BATHROOM AND KITCHEN ACCESSORIES:

TOTAL 1.288

  • MIDDLE FLOOR BATHROOM AND KITCHEN ACCESSORIES:

TOTAL 1,288

  • GROUND FLOOR BATHROOM AND KITCHEN ACCESSORIES:

TOTAL : 1288

GRAND TOTAL 3,864

Shower Cabinets :

  • UPPER FLOOR 85x210 cm Shower glass separatorıon (Antique Brass )
  • MIDDLE FLOOR 70x210 cm Shower glass separatorıon (Antique Brass)
  • GROUND FLOOR 70x210 cm Shower glass separatorıon (Antique Brass )

TOTAL : 1875

CARPENTER WORKS ( lacquer quality370 EUR per m2 and high gloss quality 270 EUR perm2 ) :

  • UPPER UNIT

Kitchen cabinets /kitchen drawers ( 270 EUR per m2) 10m: 2700 Bathroom customer made wooden cabinet 300,00 Bathroom mirror 70,00 Total :3070

  • MIDDLE UNIT:

Kitchen draws 12 m : 3240 Bathroom cabinets: 300,00 € Bathroom mirror x 1 70,00 € Total : 3610

  • GROUND UNIT

Kitchen draws 12 m : 3240 Bathroom cabinets x 1 300,00 € Bathroom mirror x 1 70,00 € TOTAL: 3610

Note :Cabinet handles are not included in the price.

Only the draws mechanisms are included Depending on the selected material, the price may vary.

Grand total 10290

LIGHTING :

  • UPPER GLOOT :4 ceiling lamps
  • MIDDLE FLOOR 4 ceiling lamps
  • GROUND FLOOR: 4 ceiling lamps
  • LOFT FLOOR: 2 ceiling lamps
  • TERACCES AND BALCONIES 8 WALLS LAMPS
  • 6 BED SIDE TABLE’s LAMPS FOR FLOORS
  • MIRTOR LAMPS FOR ALL FLORS

TOTAL : 1645

  • SWITCH and SOCKETS :614

GRAND TOTAL : 2306

FACADE WOORKS:

  • Removal of the old plaster
  • Cleaning and filling of the wall cracks
  • Garbage truck
  • Installatıon of the roof gutter
  • Application of the black plaster
  • Plastering of the windows corners
  • Apllication of the white plaster
  • Building construction of the new balcony on middle floor
  • Cleaning of the rusted ıron on the facade
  • Application of the screed plaster boards on the roof of the all balconies
  • Installation of the gathering pipes and drainages pipes
  • Build of the skelton for the restoration of the facade
  • Painting of the facade

TOTAL 12.800

CLEANING

  • Professional Cleaning from the industrial dust 7 hours per floor per person , 56 per day , 2 person per floor : 112 per floor

Total per 3 floors: 336 EUR

GRAND TOTAL2 : 194289

Management fee 15%

cash payment without tax: 29143

GRAND TOTAL 3: 223432

ADDITIONAL COSTS:

  • Transportation of Bathrooms and Lighting accessories : 1200 EUR
  • Customer TAX 448

GRAND TOTAL: 1648

  • Water tank total 1450
  • Sun panel 1200
  • 7 AC, 600 per AC total 4200
  • Furniture 3000 EUR per floor, 9000 for ground, mid and upper floor, loft 1500

Total 10500

Grand total 4 : 242430

Notes

Please consider that extra work might be ocurred and the cost can be increased to 10 %. The price might be reduced / increased for lighting, tiles , accessories dependıng on the .

Timeline Plan

  1. Complete all demolition, reconfiguration and infrastructure works in 12 weeks.
  2. All orders will be finalized by week 15.
  3. Another 5 weeks for installation and the final finishing.

On 20 th week snagging’ process, cleaning, etc.

Payment Plan:

The payments will be transferred directly to the contractors account upon the project manager request. The first payment of demolition , reconstruction and installation of new infrastructure works at the beginning of the process

Then management fee will be paid in 3 instalments;

  • 1st installment is 50 % and will be paid at the beginning of the renovation
  • 2nd installment is 30 % and will be paid after 10 weeks
  • 3rd instalment is 20 % and will be paid after finalising the renovation (in about 20 weeks)